Construction of water supply system in Emmeloord, Netherlands


Drilling work for water supply. Distance - 280 mtr. Tube diameters - 450 mm and 350 mm each. Duration of work - 3 days work.

Equipment

 FORWARD RX33×120 HDD RIG

Location

 Emmeloord, Netherlands

Project details

 Drilling work for water supply. Distance - 280 mtr. Tube diameters - 450 mm and 350 mm each. Duration of work - 3 days work.

Soil type

 Sandy and clay soils

 